CAZ (THAILAND) PUBLIC COMPANY LIMITEDSET: CAZ🇹🇭 TH

MD&A · 2025

Overview of Operations

Overview of Operations

Driven by the Group’s commitment to maintaining international standards and quality of operations, as well as its dedication to delivering projects on schedule, the Group successfully completed and delivered several projects to customers in 2025. These included the Sakura Project for the VCM/PVC area, covering fabrication and installation of piping works, structural steel and mechanical installation, as well as painting works, and the fabrication of atmospheric liquid storage tanks. In addition, the Propane Supremacy Project was completed on schedule, with a scope encompassing engineering, procurement, fabrication, and installation of the propane distillation tower (Depropanizer).

During 2025, the Company also entered into negotiations with a customer for the final settlement of a construction contract through a reduction in project value after a customer, acting as the main contractor, terminated its agreement with the project owner. As a result, the Company recognized a cumulative of project loss of Baht 928.26 million from the adjustment in project value following the contract settlement.

Meanwhile, in 2025, the Group secured new contracts through the execution of an Engineering, Procurement, Construction, and Commissioning (EPCC) agreement under a joint venture between POSCO Eco & Challenge Co., Ltd. and CAZ (Thailand) Public Company Limited (the “PEC-CAZ Consortium”). The scope of work covers the Map Ta Phut Industrial Port Development Project Phase 3 (Phase 1), specifically the gas terminal superstructure. The project includes construction and commissioning of the LNG jetty and LNG receiving and regasification facilities on approximately 200 rai of reclaimed land (for the initial gas terminal phase). The total project value is Baht 11,567.47 million. The project is located in Rayong Province, with a construction period of 45 months.

As of 31 December 2025, the Group had a total construction backlog of Baht 11,504.19 million, representing projects under construction for which revenue has not yet been recognized.

Operating Results & Financial Condition

Introduction

Revenues from construction contracts

The Group recorded revenue from construction services of Baht 3,726.80 million and Baht 2,916.52 million in 2024 and 2025, respectively.

The Group’s total revenue from construction contracts for the year ended 31 December 2025 totaled Baht 2,916.52 million, representing a decrease of Baht 810.28 million, or 21.75%, compared to the same period of the previous year, in which construction revenue totaled Baht 3,726.80 million. This decrease was primarily attributable to the recognition of revenue from construction projects on hand that had been contracted in prior years and during 2025, resulting in revenue recognition based on the percentage of completion and the transfer of control of the work to customers, which increased in 2025.

In addition, during the third quarter of 2025, the Group negotiated with a customer for the final settlement of a construction contract through a reduction in the project value after the customer cancelled the contract with a project owner. As a result, the Group recognized cumulative losses arising from the final settlement contract by reducing the contractual project value with such customer in the amount of Baht 928.26 million. The loss was primarily due to the customer requesting a reduction in the progress payments following the termination of the contract by the project owner. Consequently, the Group’s revenue from construction contracts totaled Baht 1,988.26 million, representing a decrease of Baht 1,738.54 million, or 46.65%, compared to the same period of the previous year.

As of 31 December 2025, the Group had construction projects in progress for which revenue has not yet been recognized (Backlog), totaling Baht 11,504.19 million.

Other Income

The Group reported an increase in other income totaling Baht 62.31 million, representing an increase of 540.42% compared to 2024. The Group’s other income mainly comprised gains from the sale of scrap metal, as well as unused machinery and construction materials, which increased by Baht 47.56 million compared to the previous year. Such disposals included items such as scrap metal and scaffolding.

In addition, the Group had other income from the negotiation with certain trade creditors to obtain discounts on long-outstanding payables. This was a consequential effect of delayed payments under a construction project involving a customer whose contract was for final settlement during the year, as mentioned above.

Administrative Expenses

The Group’s administrative expenses for the year ended 31 December 2025 totaled Baht 188.00 million, representing an increase of Baht 63.54 million, or 51.05%, compared to Baht 124.46 million for the same period of the previous year. The increase was primarily attributable to surcharges and penalties arising from the late payment of taxes, as well as personnel-related expenses for certain employees previously assigned to a construction project that was settled by the customer, who requested a reduction in the progress payment after the termination of the contract with the project owner. As a result of such final settlement, the affected personnel were reassigned, and their related costs were reclassified under administrative expenses. The increase also included other expenses associated with the final settlement of the construction project, as mentioned above.

Reversal of allowance for expected credit losses

As a result of the negotiation of the final settlement of a construction contract during the period, the Group recorded a loss from the reduction in the contract value in the construction revenue section in the amount of THB 928.26 million. Consequently, the Group reversed the impairment of expected credit losses related to trade receivables and contract assets from the same customer, which had been previously recorded in 2024, in the total amount of THB 548.00 million. Therefore, the net impact of the final settlement contract negotiation during the third quarter of 2025 resulted in a net loss of THB 380.26 million.

Finance Costs

The Group’s finance costs totaled Baht 40.87 million, representing an increase of Baht 7.42 million, or 22.17%, compared to Baht 33.45 million in 2024. This increase was primarily attributable to short-term borrowings obtained to support working capital requirements for the Group’s ongoing construction projects.

Assets
As at 31 December 2025, the Group had total assets of Baht 1,716.55 million, representing a decrease of Baht 1,143.87 million, or 39.99%, compared to total assets of Baht 2,860.43 million as at 31 December 2024. The changes in assets are detailed as follows:

Current assets consisted of the following:

  • Cash and cash equivalents amounted to Baht 98.19 million, representing an increase of Baht 71.20 million. This increase was primarily due to the receipt of payment from a customer with whom the Group had negotiated the final settlement of a construction project contract, as mentioned above, as well as the receipt of payment from retention receivables of one of the Group’s ongoing projects in accordance with the contractual terms.

  • Trade and other current receivables, and contract assets, decreased by Baht 435.92 million and Baht 534.01 million, respectively, representing decreases of 35.70% and 88.26%, respectively. These decreases were primarily attributable to the reduction in project value following the negotiated final settlement of a construction project contract, as well as the receipt of payments from a customer during the period.

Non-current assets consisted of the following:

  • Land, buildings, and equipment, net, increased by Baht 52.26 million. This was mainly due to the revaluation of assets amounting to Baht 147.12 million. After deducting disposals and depreciation during the period, the net carrying amount of land, buildings, and equipment totaled Baht 622.20 million.

  • Retention receivables decreased by Baht 188.89 million, as a result of the mutual agreement on the final settlement of a construction project contract with a customer.

  • Deferred tax assets decreased by Baht 109.53 million due to the reversal resulting from the reduction in project value following the negotiated final settlement of a construction project contract with a customer during the period.

Liabilities

As at 31 December 2025, the Group had total liabilities of Baht 1,220.90 million, representing a decrease of Baht 948.61 million, or 43.72%, compared to the previous year. The changes in total liabilities are detailed as follows:

  • The Group had current liabilities totaling Baht 171.61 million, representing a decrease of Baht 481.62 million from the previous year. This decrease was primarily due to the repayment of short-term borrowings obtained from financial institutions for ongoing construction projects in accordance with the agreed repayment schedules, as well as the repayment of short-term borrowings from related parties during the period.

  • Trade and other current payables amounted to Baht 501.78 million, representing a decrease of Baht 347.82 million from the previous year. This was mainly attributable to the negotiated final settlement of a construction contract with a customer and the settlement of related obligations during the period, which enabled the Group to receive partial cash inflows and subsequently repay such trade and other current payables.

  • Contract liabilities amounted to Baht 249.75 million, representing a decrease of Baht 211.20 million from the previous year. This consisted of the following:

    1. Unearned service revenue (advance billings to customers in accordance with contractual terms where the billed amount exceeds revenue recognized to date) amounted to Baht 249.75 million, representing a decrease of Baht 155.66 million from the previous year. This decrease was attributable to the recognition of service revenue upon the transfer of control over goods and services to customers in accordance with the contractual terms during the period, as well as the final settlement of a construction project contract with a customer.

    2. Advances received for construction services decreased by Baht 55.54 million. These advances related to projects contracted in prior years, and the decrease was in line with the progress billings to customers during the period. The deductions from such advances were made in accordance with the contractual terms.

  • Convertible debentures: On 2 December 2025, the Company issued 120,000 units of convertible debentures, bearing an interest rate of 6.00% per annum, with a par value of Baht 1,000 per unit, totaling Baht 120.00 million. These debentures will mature on 2 December 2027 and are convertible at a conversion price of Baht 5 per ordinary share.

Subsequently, on 16 December 2025, the Company issued the Warrants to Purchase Ordinary Shares of the Company No. 1 (CAZ-W1), free of charge, in the amount of 122.40 million units, to be allocated to existing shareholders who subscribed for the convertible debentures in proportion to their respective shareholdings, at an allocation ratio of 1 unit of convertible debenture to 1,020 units of warrants. Each warrant entitles the holder to purchase 1 ordinary share at a conversion price of Baht 0.80 per ordinary share. (Further details are disclosed in Note 19 to the financial statements.)

Shareholders’ Equity
As at 31 December 2025, the shareholders’ equity attributable to the parent company amounted to Baht 495.65 million, representing a decrease of Baht 195.26 million, or 28.26%, compared to Baht 690.91 million as at 31 December 2024. This decrease was primarily attributable to the Group’s total comprehensive loss attributable to the parent company for the year ended 31 December 2025, amounting to Baht 179.82 million.

Operating Results & Profitability

Profitability

Gross profit and net profit of the year ended 31 December 2025 and 2024 as follows;

Profitability

2025

2024

Million Baht

%

Million Baht

%

Gross profit

(599.49)

(30.15)

410.15

11.01

Profit attributable to owners of the parent

(297.44)

(14.42)

(231.70)

(6.20)

In 2025, the Group had a gross loss of Baht (599.49) million, representing a gross loss margin of (30.15%), a decrease of Baht 1,009.64 million compared to 2024, in which the Group’s gross profit was Baht 410.15 million, or a gross profit margin of 11.01%. The main reason was the recognition of a loss amounting to Baht 928.26 million resulting from the mutual agreement of final settlement of a construction project contract with a customer, as mentioned above. However, excluding such loss, the Group would have recorded a gross profit of Baht 328.77 million, which still represents a decrease compared to the same period of the previous year. This was mainly due to the revision and updating of budgeted costs for certain projects, as well as the completion and delivery of construction work to customers during the period.

In 2025, the Group had a net loss attributable to the parent company of Baht (297.44) million, representing a net loss margin of 14.42%, compared to Baht 231.70 million, or a net loss margin of 6.20%, in 2024. The increased net loss margin was mainly attributable to the recognition of losses resulting from the final settlement of a construction contract with a customer, which involved a reduction in the project value, as well as higher administrative expenses, the reversal of expected credit loss provisions, and increased finance costs, as described above. However, excluding the loss resulting from the final settlement contract, the Group would have reported a net profit attributable to the parent company for 2025 in the amount of Baht 120.98 million.

Liquidity & Capital Adequacy

For the years 2024 and 2025, the Group had net cash flows (used in) / generated from operating activities of THB (423.32) million and THB 354.18 million, respectively. In 2024, the Group had a major trade receivable with a significantly overdue outstanding balance, which resulted in negative cash flow from operating activities.

However, during 2025, the said customer terminated its contract with the Company and made partial repayments during the year. As a result, the Group recorded net cash inflow from operating activities totaling THB 354.18 million for the year.

Cash flows (used in) investing activities for the years 2024 and 2025 amounted to THB (125.05) million and THB 126.45 million, respectively. The Company’s key investments included the purchase of equipment and machinery, as well as additional intangible assets, to support the expansion of its construction contracting services compared to the previous year. In 2025, the Group also disposed of equipment and scrap steel, resulting in positive cash flow from financing activities.

Cash flows from financing activities (used in) for the years 2024–2025: In 2024, the Group received cash inflows from short-term and long-term borrowings totaling THB 401.63 million to be used as working capital and for ongoing construction projects. In contrast, in 2025, the Group repaid such borrowings after receiving payments from a customer during the year, resulting in cash outflows from financing activities totaling THB 409.44 million.

Debt Securities with Financial Ratio Requirements

Debt Securities with Financial Ratio Requirements Issued?

No

Factors That May Affect Financial Condition

Factors or Incidents That May Materially Affect Financial Condition

The Company’s business operations depend largely on investments in engineering construction projects serving the petrochemical, oil, gas, energy, and infrastructure industries. The expansion of these industries, together with investment policies of both the public and private sectors, plays a significant role in creating opportunities for the Company to secure new projects. Any slowdown in investment in these related industries may affect the Company’s project volume and revenue in the future.

In addition, the construction business is sensitive to fluctuations in raw material prices, labor costs, and operating expenses, as well as the Company’s ability to manage and complete projects within the specified timeframe and budget. Significant increases in costs or delays in project execution may adversely affect the Company’s profit margins and operating results.

Meanwhile, the existing backlog and the ability to consistently bid for and secure new projects are key factors supporting the stability of the Company’s future revenue. This includes maintaining financial liquidity and managing working capital effectively to support large-scale projects. The Company prioritizes and closely manages these factors to ensure sustainable long-term business growth.

Contents